Submission and assessment of the inquiry. Followed by the processing of the inquiry and preparation of an offer. Once the offer is agreed the contract is being signed.
Technical consultation regarding the design of a specific part, concept of an injection mould and customer’s requirements regarding quality.
Development and design of an injection mould in CAD/CAM system Unigraphics (including the mould flow analysis) takes approximately 3-4 weeks
Once the construction is signed off, the production of the injection mould begins in our own tool shop. The production takes 8-12 weeks depending on the complexity and the number of cavities.
Testing the mould in own moulding department followed by an immediate dispatch of the first samples to the customer. The complete measurement report (ISIR) is sent additionally.
Possible corrections of injection mould and its final approval by the customer for serial production.
Moulds are packed according to the customer specifications and delivered by an internal or an external carrier.